What a uranium plant does

Uranium is a heavy metal that is mined for fuel for nuclear power stations. The ore holds very little uranium, often a fraction of one percent, so a plant has to separate a small amount of uranium from a large amount of rock. The product is a concentrate of uranium oxide, called yellowcake, packed in drums. Fuel is made from it elsewhere, in other plants.

There are two main routes. In a conventional plant the ore is mined, crushed, ground and leached with acid, and the uranium is taken out of the solution. In in-situ recovery the ore stays in the ground and a solution is pumped through it. The two routes share the last steps. Each major unit has its own lesson: click it in the animation. This lesson is education about principles. Uranium and its products are radioactive and tightly regulated: licences, radiation protection rules and safeguards apply to every step, and nothing here is a procedure.

How it works

In the conventional route the solids go one way, from the ore to the tailings, and the uranium goes with the liquid from the leach to the drums.

  1. 1Crush and grind. The ore is crushed (see jaw crusher), carried on a conveyor and ground with water in a ball mill to a slurry of fine particles, so that the acid can reach the uranium minerals.
  2. 2Leach. The slurry flows through a row of stirred tanks. Sulphuric acid and an oxidant dissolve the uranium out of the minerals into the liquid. A few hours to about a day of time in the tanks are needed. Some mines leach crushed ore in heaps instead (see heap leach).
  3. 3Separate and wash the solids. The leached slurry goes to thickeners. The solids settle and are washed so that the uranium solution is not thrown away with them. The clear solution that holds the uranium overflows, and it is clarified.
  4. 4Concentrate and clean by solvent extraction. The clear solution goes to solvent extraction. An organic liquid takes the uranium out of the solution and a second stage gives it up into a small volume of strong solution. Some plants use ion exchange resin for this step instead.
  5. 5Precipitate, dry and pack. A reagent makes the uranium come out of the strong solution as a solid, which is thickened, filtered, washed, dried and packed in sealed drums (see precipitation and drying).
  6. 6Store the tailings. The washed solids and the solution that is left after extraction (the raffinate) are neutralised and sent to a tailings storage facility, which is designed, licensed and monitored to keep the waste secure for a very long time.
  7. 7The other route: in-situ recovery. Where the ore is a water-bearing sand, a solution is pumped down wells, dissolves the uranium in the ground and is pumped up again (see in-situ recovery). The uranium is caught on resin at the surface and the strong solution that is washed off the resin goes to precipitation, just as in the conventional route.

The numbers

Typical figures, which depend on the ore and the plant: an ore of roughly 0.05 to 0.3 percent U3O8; grinding to roughly 0.1 to 0.5 mm; a leach slurry of roughly 35 to 50 percent solids at a pH of about 1 to 2 and a temperature of roughly 30 to 50 °C; a leach of roughly 6 to 24 hours; an acid use of roughly 10 to 50 kg for each tonne of ore; and an overall recovery of roughly 85 to 95 percent.

Worked example. Assume 1,000 t of ore a day at 0.10 percent U3O8, a leach that dissolves 92 percent, a recovery of 98 percent of the dissolved uranium through extraction and precipitation, a product of 75 percent U3O8, drums of 400 kg, an acid use of 25 kg/t, a leach slurry of 40 percent solids with a density of 1.34 t/m³, a leach time of 12 hours, and three leach tanks.

QuantityWorkingResult
Uranium in the ore1,000 t/day × 0.10 percent1.0 t/day of U3O8 (1,000 kg)
Dissolved in the leach1,000 × 0.92920 kg/day
Recovered as product920 × 0.98901.6 kg/day
Overall recovery0.92 × 0.9890.2 percent
Dry product at 75 percent901.6 ÷ 0.75about 1,202 kg/day
Drums of 400 kg1,202 ÷ 400about 3 a day
Acid1,000 t × 25 kg/t25 t/day
Slurry flow at 40 percent solids(1,000 ÷ 24 = 41.7 t/h of ore) ÷ 0.40104.2 t/h, or 77.7 m³/h at 1.34 t/m³
Leach volume at 12 hours77.7 m³/h × 12 h933 m³, three tanks of about 311 m³

Assumed inputs, not data from a particular plant. A real plant has losses to the tailings, a bleed to keep impurities down, and often several leach and wash stages.

Safety: the acid, the organic liquid and the reagents are hazardous, and the ore, the process liquids, the product and the tailings are all radioactive to some degree. This lesson is education about principles. Uranium and its products are radioactive and tightly regulated: licences, radiation protection rules and safeguards apply to every step, and nothing here is a procedure.

What the operator watches

  • Leach conditions. Acid, the oxidant, temperature and time decide how much uranium dissolves.
  • Uranium in the tailings. It shows how much was left behind in the solids and the raffinate.
  • Solution clarity. Solids that are carried into solvent extraction cause trouble there.
  • Radiation and dust. Monitoring and control of both are part of every operating day.

Common problems

  • Slow or low leach. Coarse grinding, too little acid or a weak oxidant leave uranium in the solids.
  • Solids in the solution. Poor settling lets fine solids into solvent extraction, which makes crud.
  • Impurities. Other metals that dissolve in the acid take up extractant, acid or reagent.
  • Scale. Solids build up in tanks, pipes and filters.

Words you will meet

Yellowcake
The dried uranium solid that is sold, counted as U3O8.
Leach
Dissolving the metal out of the ore with a liquid.
Pregnant solution
The solution that holds the dissolved uranium.
Solvent extraction
Taking a metal out of a solution into an organic liquid.
Raffinate
The solution left after the metal has been taken out.
Precipitation
Making a dissolved substance come out as a solid.
Tailings
The waste solids left after the metal has been taken out.
In-situ recovery
Dissolving the metal in the ground and pumping the solution out.

Check your understanding

Why must the ore be ground before it is leached?

The uranium is held inside the mineral grains. Fine grinding lets the acid reach them, so more of the uranium dissolves in the time available.

Why is the uranium taken out of the solution in two steps, extraction and then precipitation?

The leach solution is large and holds many other dissolved metals. Solvent extraction picks out the uranium and puts it in a small volume of clean solution, so that precipitation makes a clean, concentrated product.

What is the main difference between a conventional plant and in-situ recovery?

In a conventional plant the ore is dug up, ground and leached at the surface, and ground rock is left as tailings. In in-situ recovery the ore stays in the ground, and only the solution is brought up.

Key facts

Product
Yellowcake: uranium oxide in sealed drums.
Typical ore
About 0.05 to 0.3 percent U3O8.
Conventional route
Crush, grind, leach, thicken, extract, precipitate, dry.
Other route
In-situ recovery with wells and resin.
Regulation
Licences, radiation protection and safeguards apply.
Use the animation
Follow the ore from the crusher at the top of the picture along the conveyor into the mill, then down the row of three glass leach tanks. The purple pipe adds acid. The thickener comes next: the overflow goes to the solvent extraction pair, and the underflow goes to the tailings storage in the front right corner. The strong solution goes to the glass precipitation tank, the dryer and the drums. The cutaway of the ground in the front left shows the other route, in-situ recovery. The numbers on the drawing match the numbered steps. Click a piece of equipment to open its own lesson, or hover over any part for its name and what it does.