Deliverable Register

Maintain the master list of documents to be produced and handed over on a project, tracking type, discipline, tier, status, progress, responsibility and dates. With the Management module, plan the hours first in the project estimate.

Overview

The Deliverable Register is the per-project document delivery register — the master list of every document to be produced and handed over. It tracks each deliverable's type, discipline, criticality tier, status, progress %, responsible person, and planned/forecast/actual dates.

  • Deliverables can be linked to real documents in the system (cPD, cTD, cPFD, Datasheet, List, Calculation, Piping System, Specification, IsoMet) or stand alone as Other — ten deliverable types in all.
  • The register powers a Project Completeness percentage.
  • View every project's register from one global page, sorted by due date.

Access & Permissions

  • Any project member can view the register.
  • Add, edit, link, unlink, and export require edit rights on the project (or superadmin).
  • No changes are allowed once the project is archived.
  • The global page is only shown in the menu to users who can create projects.

Adding a Deliverable

  1. Open your project and go to the Deliverable Register (or the Deliverables section on the project page).
  2. Click + Add Deliverable to reveal the inline form.
  3. Fill in the fields (see below) and click Add Deliverable.
  4. For any type other than Other, EngCoSuite also creates a real document file at Rev A (“Created from Deliverable form”) and auto-links it to the deliverable.
The deliverable register of one project: every document, its status and its progress.
The deliverable register of one project: every document, its status and its progress.

Deliverable Fields

  • Type — one of ten: cPD, cTD, cPFD, Datasheet, List, Calculation, Piping System, Specification, IsoMet, or Other.
  • Existing Document — Create New, or pick an existing project document (choosing one locks the Doc # and Title to it).
  • Doc # — e.g. P&ID-001.
  • Title — required.
  • Type-specific fields — e.g. length/diameter units for cPD, component type for Datasheets, list type for Lists.
  • Discipline — Process, Mechanical, Piping, Electrical, Instrumentation, Civil, HSE, or Other.
  • Tier — T1 - Critical, T2 - Significant, T3 - Standard.
  • Planned Date / Forecast Date / Actual Date — schedule tracking.
  • Responsible — unassigned or a team user.
  • Notes, and the Handover and Client Approval checkboxes.

Editing & Progress

  • Click the pencil icon to edit the row — Doc #, Title, Type, Discipline, Tier, Status, Progress %, dates, Responsible, Notes, Handover, and Client Approval.
  • Update Progress % from the row, or type directly into the inline percent box on the project page (AJAX, recalculates project completeness instantly).
  • Setting progress to 100% automatically forces the status to As-Built.
  • Delete soft-deactivates the deliverable (shown strikethrough on the project page); a Reactivate (+) button brings it back.

Linking Documents

  • Click the green link icon and choose the document type, then the document, then Link.
  • Only active documents of this project can be linked — deactivated documents, and documents from other projects, are not offered.
  • Linked rows show a green badge with the document name and an Unlink icon.
  • Linking fills the Doc # automatically if it was empty.

Statuses & Tiers

StatusWhen it applies
Issued for DesignDesign stage issue
Issued for Internal ReviewSent for internal checking
Issued for Client ReviewSent to the client for review
Issued for TenderIssued for tender purposes
Issued for ConstructionFormally issued for construction
As-BuiltCompleted (auto-set at 100% progress)

Tiers mark criticality: T1 Critical, T2 Significant, T3 Standard. The register filter row lets you view All / Overdue / Due Soon / Unlinked, plus per-type buttons (cPDs, cTDs, cPFDs, Datasheets, Lists, Calculations, Piping Systems, Specifications, IsoMets).

The Global Register

  • The /deliverables page shows all deliverables across your projects, sorted by due date.
  • Stats at the top: Total / Complete / Overdue / Due Soon (7 days), plus a Project Completeness progress bar.
  • Filter by project or by status (All / In Progress / Overdue / Due Soon / Complete).
  • The Days column shows Done, Today, Xd, Xd late (red row), and Xd (warning ≤ 7 days).
  • Use the View Register eye icon to jump into a specific project's register.
The global register across all your projects.
The global register across all your projects.

Exporting to CSV

  • Click Export CSV (top-right, requires edit permission).
  • Downloads {project_number}_deliverables.csv with Doc #, Title, Type, Discipline, Tier, Status, Progress %, Responsible, Planned/Forecast/Actual dates, Handover, Client Approval, and Notes.

The project estimate

The project estimate works out how many hours the project will take, role by role, before the register exists. You pick tasks from your company's estimating template, say how many of each, and the page adds the hours up. Once the estimate is approved it can generate the Deliverable Register, with budget hours already on every row.

  • Needs the Management module of the project's organisation (Super Admins are exempt). Clients never see it.
  • Open it with the Estimate button on the project page or on the Deliverable Register page. Anyone on the project who can open it can look at it and export it.
  • Change it: project editors, the organisation's admin and Super Admins. Everyone else sees it read-only.
  • The checker, approver and author of its review may open it even when they are not on the project team, but they cannot change it.

The estimating template

The template is the list of tasks (a drawing, a calculation, a datasheet, a HAZOP, a month of project management …) with the hours each takes. EngCoSuite supplies a starting template of more than 120 tasks in eight disciplines. The first time your organisation opens it, it is copied and from then on the copy is yours: later improvements to our template never change it.

  • Who: the admin of an organisation that has the Management module, and Super Admins. Menu: Doc Control → Estimating Template.
  • Roles: five columns of hours — by default Drafting, Drafting check, Engineering, Engineering check and Project management. You can rename them. Leave a role's hours empty when it is not involved (a calculation has no drafting).
  • Columns: Ref, Task, Deliverable (the kind: drawing, calculation, datasheet …), Unit and the hours per role. The unit is what one set of hours buys and what the estimate's Qty counts: each, per week or per month. Hours are whole numbers, always rounded up.
  • Edit: change hours, rename roles and disciplines, + Add a task (your own tasks get references like CUS-001), remove tasks you never do, then Save.
  • CSV: Save this template to a CSV file lets you edit the whole list in a spreadsheet. Import from a CSV template then replaces all the tasks (after a confirmation); a bad row refuses the whole file.
  • Reset to EngCoSuite's template throws your copy away and starts again from ours.

Changing the template never moves an estimate that already exists: hours are copied onto a line when you add the task.

Building the estimate

  1. Open the project's Estimate page. Lines sit in WBS sections (the work breakdown). With an empty estimate, press + Add WBS and name the section — for example a discipline or an area of the plant.
  2. In a section press Add Predefined tasks to pick tasks from your template (filter by reference, task or unit, then Add selected), or Add Blank row for a task of your own. In the picker, Add to chooses the section.
  3. For each line set the Qty (counted in the Unit: each, per week or per month) and the Factor: how hard this job is, where 1 is typical, 0.6 simple and 1.6 complex.
  4. Press Save. The Save button stays at the bottom of the window and shows Unsaved changes; the page also asks before you leave with unsaved changes.
ThingHow it works
Hours of a lineFor each role: the template hours per unit × Qty × Factor, rounded up to a whole hour. The line's Hours is the sum over the roles. Example: 3 h × Qty 2 × Factor 1.25 = 7.5, shown as 8 h.
Typing an hour boxChanges that line only, never the template. What you type is the hours of the whole line, at the Qty and Factor it has now.
Summary at the topTotal hours per role with their share, total hours and days of 8 hours, and hours by WBS section. It moves as you type.
Column widthsDrag the right edge of a column heading to make that column wider or narrower; every WBS section follows, so the columns stay in line. Double-click the edge to put that column back to its standard width. The widths are kept in your browser, not in the estimate.
SectionsRename a section by typing in its name box. + Add WBS under a section inserts a new one after it; an empty section has a × to remove it. The arrow at the left collapses a section (the tasks are hidden, not removed).
Moving thingsDrag the move icon of a line to another place or section, or of a section to reorder sections. A green line shows where it would land; Esc cancels. Desktop browsers only, not touch screens.
Removing a lineThe × at the end of the row.
Limits500 lines and 40 WBS sections in one estimate. Qty must be 0 or more, the Factor above 0 and up to 100.

Review, approval and the register

An estimate is in one of these states, shown in a banner at the top of the page:

StateWhat it means
DraftNot yet sent for review (or its review was cancelled). Lines can be changed, and the Excel import is available.
Sent for review / CheckedWith the checker, then with the approver. The estimate is locked meanwhile.
Sent backThe reviewer asked for changes. Read the comments in the workflow, change the estimate here and save, then use Resubmit in the workflow.
ApprovedLocked. Generate Deliverable Register appears.
BaselineThe register was generated from it. The estimate is read-only for good, and the banner compares the register's size now with the baseline.
  1. Send for review (needs a saved estimate with at least one line): choose the Checker and the Approver and the Days allowed for each step. They must be an Org Admin, a Manager or a Senior Engineer of the organisation. It then runs as an ordinary workflow; Change people works on it too, and View Estimate on the workflow page takes the reviewer back to the lines.
  2. The reviewer comments on a line or a single cell (Qty, Factor, hours): hover the cell and use the comment button. Only the person who holds the estimate at that moment can write comments.
  3. Generate Deliverable Register is a one-time step. It tells you how many deliverables and actions it will make and asks you to confirm. Each document line (drawing, 3D model, calculation, specification, datasheet, register, report) counted in each makes as many register rows as its Qty (rounded up); every other line counted in each (project management, a HAZOP, a site visit …) makes actions; a per week or per month line makes one recurring action carrying the whole line's hours. A line may make up to 200 rows, an estimate up to 1000.
  4. Each new row carries its budget hours per role (the line's hours shared as evenly as whole hours allow). On the register they show in the Budget h column, with a Kind filter (all, deliverables, actions) and the Assign people… button to name a person per role. Percent complete for such rows is worked out from the hours of each role and the progress of each role.

Export to Excel and PDF

Anyone who can open the estimate can export it, in any state.

  • Export PDF — Estimate_{project}_{date}.pdf, landscape A4: the lines by WBS section with the hours of each role, the state of the estimate (draft, under review, approved by whom and when, or baseline), then a summary by role and by discipline.
  • Export Excel — Estimate_{project}_{date}.xlsx, a workbook for someone who is not on the system. It has three sheets:
    • Instructions — the project, state, who exported it and how to use the workbook.
    • Estimate — one row per line. The yellow cells are the inputs: WBS section, Ref, Task, Discipline, Deliverable, Unit, Qty, Factor, hours per unit for each role, and Note. Discipline, Deliverable and Unit are drop-down lists. The hours of each role and the line total are live formulas (hours per unit × Qty × Factor, rounded up to a whole hour), so they follow when the file is changed; the total row at the top adds them up. Spare rows below the last line add up too.
    • Summary — formulas for the totals by role, by discipline and by WBS section.
  • The workbook also carries a hidden, signed sheet and a hidden Line id column. EngCoSuite reads the file back through them, so do not change or delete them, and keep the column order.

Import from Excel

When someone has changed the exported workbook (a colleague or the client, outside EngCoSuite), bring their changes back with Import from Excel. The button is there for people who can edit the estimate, and only while it can be changed: as a draft or after it was sent back.

  1. Press Import from Excel, choose the .xlsx file and press Check the file.
  2. The dialog shows what would happen, and nothing is stored yet: a count such as “4 lines changed, 2 added, 1 removed, 90 unchanged”, any warnings, and a list of the changes in words (the first 80, with “and n more” after them).
  3. Press Apply to the estimate to store it, or Close to leave the estimate as it is. The check expires after 30 minutes and works once; if it has expired, choose the file again.
  4. If the page has unsaved changes, you are asked first: the import replaces the saved estimate, so those changes would be lost.

What happens to each line

In the fileIn the estimate
A row with its line id and different valuesChanged: the line takes the file's section, Ref, task, discipline, deliverable, unit, Qty, Factor, hours per unit and note. The change is listed in words, for example which hours went from what to what.
A row with its line id and nothing differentUnchanged.
A row without a line id (typed in a free row)Added as a new line. It needs a Task, a Discipline and a Deliverable from the lists, a Unit and a Qty. A WBS section name that does not exist yet creates that section.
A line of the estimate that is missing from the file (row deleted or cleared)Removed.
A row with a bad number, no task, no quantity, or a discipline / deliverable not in the lists on a new lineSkipped, with a warning naming the row. On an existing line a mistyped discipline or deliverable keeps the old one, with a warning.

When the file is refused

  • It is not an .xlsx file (an .xls, a macro workbook .xlsm, a CSV or a PDF), is larger than 10 MB, or cannot be opened.
  • The hidden signed sheet is missing or was changed, or the columns of the Estimate sheet were moved or renamed.
  • It was exported from another project's estimate — a signed workbook from another project is never accepted.
  • The roles of the estimating template changed after the file was made. Export the estimate again.
  • The file has no lines.
  • The estimate is under review, approved or already the baseline: it cannot be changed, so it cannot be imported either.
  • The file breaks one of the page's own rules (a unit that is not each / per week / per month, a quantity below 0, more than 500 lines …); the message says which.

If the estimate was saved again after the file was exported, you get a warning with the date: applying the file replaces those later changes with what is in the file.

Troubleshooting

IssueWhat to do
“This project is archived. Deliverables cannot be modified.”Re-open the project or ask the project owner; archived projects are read-only.
My deliverable is stuck at one statusSet Progress to 100% to automatically move it to As-Built.
I created a deliverable but don't see a document fileType Other doesn't create a file. For real types, the document was created at Rev A and is linked.
There is no Estimate buttonThe estimate needs the Management module of the project's organisation, and is not shown to clients.
The estimate will not save, or Import from Excel is missingThe estimate is under review, approved, or already the baseline of the register. Only a draft, or an estimate that was sent back, can be changed.
“This file was exported from another project's estimate”Use the workbook exported from this project's own estimate page; a signed workbook from another project is refused.
I can't edit or exportChanges and CSV export require project edit rights (or superadmin).

FAQ

What is Project Completeness?

A percentage calculated from the register, updated in real time as deliverable progress changes.

Can a deliverable point to an existing document?

Yes — pick it from the Existing Document dropdown, or link one later with the link icon.

How do I track a deliverable that isn't one of the nine document types?

Use type Other — it doesn't create a system file but tracks the item like any other deliverable.

How are the hours of an estimate line worked out?

For each role: the template hours per unit × Qty × Factor, rounded up to a whole hour. The line's hours are the sum over the roles.

Can I change the estimate after it is approved?

No. While it is under review or approved it is locked. If the reviewer sends it back you can change it again; once the Deliverable Register has been generated from it, it is the baseline and stays read-only.

What does Import from Excel do to lines that are not in the file?

They are removed from the estimate. You see the list of added, changed and removed lines before anything is stored, and can close the dialog to cancel.

Does deleting a deliverable delete the document?

No — delete only soft-deactivates the register row; the linked document file is untouched.